WELCOME

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

As we receive construction updates from the developer, we then communicate this information to the purchasers. It is an exciting process, literally watching your apartment come to life.

PROJECT:
Casey Green

96-166 Centre Rd,
Narre Warren


DEVELOPER:
Osanrae


ARCHITECT:
Demaine


BUILDER:
Demaine


Project update

  • Expected Construction Completion: End 2020/Early 2021
  • Expected Settlement: End 2020/Early 2021
  • Contact: admin@osanrae.com.au

Stage 6 Project Update - September 2020

The following works have taken place on site since the last update:
  • Timber framing works 90% complete
  • Structural steel works 100% complete
  • External cladding works 80% complete
  • Windows and roof tile works 90% complete
  • Plastering works 80% complete
  • Internal fitout and finishing works commenced
  • Driveways and external fencing works 80% complete
  • Landscape works commenced

Works planned on site for the next quarter of 2020:
  • Completing all remaining internal and external works
  • Performing final cleans and defect inspections
  • Preparing for settlement and handover

Anticipated settlement:
Lots 106 to 116 – End 2020
Lots 117 to 127 – End 2020
Lots 241 to 245 – End 2020
Lots 139 to 150 – Early 2021

We will continue to update quarterly. In the meantime, if you have any queries regarding the development please contact nhan@360propertygroup.com.au.




PROJECT:
River One

6 Joseph Road,
Footscray


DEVELOPER:
Blue Earth


ARCHITECT:
CHT Architects


Project update

  • Expected Construction Completion: Early 2021
  • Expected Settlement: April 2021
  • Contact: meg@blueearth.com.au

March 2021

River One is well advanced and nearing completion. The building structure has now been completed, and we are currently peeling back the scaffolding showcasing the beautiful simple architectural elements of the building. Internally, all the contractors are working cohesively to deliver the project to the highest standard in a timely and orderly manner. Kitchens, bathrooms, plastering, and tiling are a work in progress, as well as all the wonderful, shared spaces including the green gardens, business centre, and the multitude of entertainment zones.
 
Moving forward, we will provide you with some helpful hints to guide you through the settlement process.

Our team have a dedicated contact person as the point of contact for all matters relating to the settlement.

We will advise of settlement timing, assist with finance enquiries, as well as conduct bank valuation and purchaser inspections.

In relation to the programme, the status is as follows:
 
Programme
The key programme items are as follows:
            
Stage                                     Status
  1. Site set up works                   Completed
  2. Bulk excavation                   Completed
  3. Basement works                   Completed
  4. Structure works                     Completed
  5. Services rough in                  Completed
  6. Window glazing                    Completed
  7. Facade cladding                 Completed
  8. Internal fit out works            In progress
  9. Finishing works                      In progress
  10. Title registration                    In progress
  11. Occupancy permit             In progress
  12. Ready to settle
 
 
Settlement Date
Settlement is anticipated for early July 2021. 

We will keep you updated as we get closer to this date.

Legal Matters
For legal matters, please ensure you continue to liaise with the legal representative. They will require a fully executed copy of the Contract of Sale as a starting point. If a legal representative is yet to be appointed, please ensure it is done so immediately.

Finance Application
If finance is required to settle the apartment, you need to ensure you are working diligently with them to ensure all documentation is in place in readiness for settlement. Please note the application process is longer, and significantly slower. If a financier is yet to be appointed, please ensure it is done so immediately.

Bank Valuation
The financier may require a bank valuation inspection to be carried out in order to complete the loan application.
 
The bank valuation inspections are by appointment only and must be booked through us. 

In due course we will provide you will details on the valuation process. 
 
At this stage, we expect valuations to commence early June 2021. We will advise you of a firmer date with our next update.

Final Inspection Appointments
The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only. 

Again, the final inspection will be by appointment only and must be booked through us.

We will advise you of firmer date with our next update.

Contact Person
Meg is your dedicated contact person for all matters relating to construction updates and settlement. Meg’s details are as follows:
 
Name:            Meg Loughridge 
Email:            meg@blueearth.com.au
Phone:           0427 444 444


PROJECT:
Flockmill Homes

22 Hardy Street,
Brunswick


DEVELOPER:
Roth Developments


BUILDER:
Saw Constructions


Project update

  • Expected Construction Completion: Stage 1: April 2021, Stage 2: October 2021
  • Expected Settlement: Stage 1: May 2021, Stage 2: November 2021
  • Contact: info@360propertygroup.com.au

April 2021

STAGE 1 COMPLETION Lots 17-39
The construction works for stage one is still on target for completion first week of May 2021.

The registration of titles is the main milestone for settlements.

At present we are forecasting that titles can be registered by the third week of May and settlements to commence before the end of May 2021.

Roth Developments are your point of contact for settlement information and coordination, please refer to Geoff Thomas - geoff.thomas@gmprojectmgt.com.au for all pre-settlement inspection, valuation and handover enquiries.

STAGE 2 COMPLETION Lots 1-16 & Lots 42-59
The construction works for stage two are still on target for completion by end of October 2021.  With a settlement process similar to the stage one process we anticipate settlements to commence before the end of November 2021. This stage of works is some time away and we will continue to update purchasers if there is any change in the forecasted completion.

The only remaining works to the project is the completion of Lot 40 & 41 the display suite that will be completed post the completion of stage 2 and not impact on the opening of the park and the balance of the development. Noting that the park is to be completed in conjunction with stage one works. Roth will be in touch closer to the time with a settlement timeline similar to the above for stage one.

To keep up to date with the happenings on site follow @rothdevelopments on Instagram.



PROJECT:
Lora Bentleigh

17-19 Loranne Street,
Bentleigh


DEVELOPER:
Taylors Reynolds


Project update


June 2020
On the midst of these surreal times, it is business as usual at Lora Bentleigh. The Ground and First Floors are well underway with plastering. Levels two and three service rough in has been completed with windows on all levels installed.

It has been exciting watching the roof install and the external brickwork and cladding are ongoing.

As we will be sending out regular, important information from now until settlement, we need to ensure we have your correct contact information. Should your contact details change, please notify us at vhogg@360propertygroup.com.au

If you have any further enquiries or your contact information changes, please contact Vicki Hogg on vhogg@360propertygroup.com.au.




PROJECT:
Fitzroy House

71-75 Arygle Street,
Fitzroy


DEVELOPER:
Piccolo


ARCHITECT:
Hecker Guthrie


Project update


April 2021
Further to their last update, Piccolo are pleased to advise that they are continuing to make excellent progress at Fitzroy House.

Since our last update a milestone was reached with the removal of the cranes, the building is now at lock-up stage. Lifts have been installed and finishing trades are systematically working their way up the building, plastering is now complete on all levels and the install of joinery, floor and wall finishes is well underway.

Works are scheduled for completion in September 2021 when we look forward to welcoming you to your new home.

With settlements approaching it is important to have your financial arrangements in place. To arrange appointments for valuation inspections please contact Stacey Korp at Piccolo's office on 9349 0000 or stacey@piccolo.net.au

https://www.youtube.com/watch?v=R7uXvXUW3ag&feature=youtu.be

For further information, please contact info@360propertygroup.com.au


PROJECT:
Park Lane

22-26 Riddell Parade,
Elsternwick


DEVELOPER:
Citiplan


ARCHITECT:
Jackson Clements Burrows Architects


Project update


November 2020
We're pleased to inform you that construction on site at Park Lane, Elsternwick is progressing well. Basement works and concrete structure are completed to level 4, with level 5 due to be completed next week.

Construction is on track for completion which is anticipated to take place in October 2021.

We look forward to bringing you more updates on the construction of Park Lane as it progresses along towards its completion.

If you have any further enquiries or your contact information changes, please contact the Development Manager, Thomas Cornelius at thomas@citiplan.com.au or on 0418 589 032.


PROJECT:
Ivanhoe Gardens

56-58 Myrtle Street,
Ivanhoe


DEVELOPER:
Blue Earth


Project update

Expected Construction Completion: August 2021
Expected Settlement: Sept/Oct 2021
Contact: meg@blueearth.com.au or 0427 444 444

March 2021

Ivanhoe Gardens continues to progress to programme.
 
We have completed the basement works and have commenced the structure completing Building A. 
Building B structure completed to Level 9, only three more levels to be completed by May 2021. 
 
As we work our way up the structure, we will commence the cladding works. The cladding works will incorporate the window systems, all feature architecture elements, wall finishing, and balustrading. 
 
As the apartments become watertight, we will commence the services rough in, with internal fit out works to follow.
 
In relation to the programme, the status is as follows:

Construction Programme

Site set up works - Completed
Bulk excavation - Completed
Ground works - Completed
Structure works - Completed Building A/In progress Building B
Services rough in - In progress
Window glazing - In progress
Facade cladding - In progress
Internal fit out works - In progress
Finishing works
Title registration
Occupancy permit
Ready to settle

Moving forward, we will continue to provide you with regular updates.

Settlement Date

Settlement is anticipated for Sept/Oct 2021.

We will keep you updated as we get closer to this date.

PROJECT:
Trentham House

12-14 Trentham Street,
Sandringham


DEVELOPER:
Carpe Group


ARCHITECT:
Martin Friedrich Apartments


Project update


CONSTRUCTION UPDATE WINTER 2021
Carpe Group
 
We hope this update finds you and your loved ones well.

Sinjen continue to make great progress. Since our last update the internal wall and ceiling linings have been completed along with tiling works.  
The joinery, stone and flooring installation is well underway with appliances to follow in due course. Below are the latest progress photos.

As previously noted, Sinjen’s revised contract completion date is 20 September 2021. Sinjen are targeting a mid-August 2021 completion. If this is achieved then settlements are likely to occur in late August through to early September 2021.

Purchaser's solicitors will be contacted by ours in due course to arrange pre-settlement inspection and advise of next steps. We will shortly be issuing a FAQs via email to answer some of the common questions that are being asked.

This will be the last formal construction update issued. If you have any queries, please do not hesitate to contact us.


Make an enquiry