WELCOME

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

As we receive construction updates from the developer, we then communicate this information to the purchasers. It is an exciting process, literally watching your apartment come to life.

PROJECT:
Park Lane

22-26 Riddell Parade,
Elsternwick


DEVELOPER:
Citiplan


ARCHITECT:
Jackson Clements Burrows Architects


Project update


June 2020
Construction on site at Park Lane, Elsternwick has commenced, with the demolition of the existing structures completed in April. Capping beam works are complete and excavation has commenced and will continue throughout June.

We look forward to bringing you more updates on the construction of Park Lane as it progresses along towards its completion.

If you have any further enquiries or your contact information changes, please contact the Development Manager, Thomas Cornelius at thomas@citiplan.com.au or on 0418 589 032.








PROJECT:
The Kent Residences

382 Burwood Road,
Hawthorn


DEVELOPER:
CDG Group


ARCHITECT:
David Hicks


Project update

  • Expected Settlement: Late November 2020
  • Contact: tania@settlement-solutions.com.au or 03 8582 8973

October 2020

We are pleased to advise you that construction is on track and apartments will be ready for bank valuation inspections from Wednesday, 28 October 2020.

Valuers must contact Tania Torres on 03 8582 8973 or email tania@settlement-solutions.com.au to make an appointment.

Please note that these inspections are for bank valuers only. You will have an opportunity to inspect your apartment shortly after this date.


PROJECT:
Ivanhoe Gardens

56-58 Myrtle Street,
Ivanhoe


DEVELOPER:
Blue Earth


Project update

Expected Construction Completion: August 2021
Expected Settlement: September 2021
Contact: meg@blueearth.com.au or 0427 444 444

September 2020

Ivanhoe Gardens continues to progress to programme!

Ivanhoe Gardens is progressing to programme thanks to the great work of Hamilton Marino.

The lowest basement level is now complete, with excavation and piling works also now complete. As we progress through the below ground works, we will start erecting basement 2 and basement 1 slabs.

By the end of November, we expect to complete all basement levels. Once the basement slabs are complete, we will commence above ground structure.

In relation to the programme, the status is as follows:

Construction Programme

Site set up works - Completed
Bulk excavation - Completed
Ground works - In Progress

Moving forward we will continue to provide you with regular updates.

PROJECT:
Flockmill Homes

22 Hardy Street,
Brunswick


DEVELOPER:
Roth Developments


BUILDER:
Saw Constructions


Project update

  • Expected Construction Completion: Stage 1: Q2 2021, Stage 2: Q3 2021
  • Expected Settlement: Stage 1: Q2 2021, Stage 2: Q3 2021
  • Contact: info@360propertygroup.com.au

July 2020
Construction is moving along, on schedule, despite stricter OH&S guidelines due to the COVID-19 pandemic.
Most ground slabs are now complete with framing up on about 50% of the lots. Roofs are currently being installed on Hardy St townhouses along with services rough in. Construction completion dates have not changed since the prior update.

For further information, please contact us at info@360propertygroup.com.au.


PROJECT:
Fitzroy House

71-75 Arygle Street,
Fitzroy


DEVELOPER:
Piccolo


ARCHITECT:
Hecker Guthrie


Project update


September 2020
Fitzroy House construction continues to make good progress. We are now half way through the above ground structural works with the pouring of level 4 concrete slab now complete.

We trust that you enjoy the latest footage from site:

https://www.youtube.com/watch?v=RBFWG1uSYsc

The main focus on-site is structure completion and preparation for rough-in off services.  Offsite works are also continuing with the fabrication of the facade and internal joinery elements about to commence.
 
Due to current restrictions we have experienced some delays in our program.  However, with upcoming relaxation to these restrictions we hope to minimise further delays. We will confirm the revised program in the coming months.

We look forward to keeping you updated on progress later in the year.

For further information, please contact info@360propertygroup.com.au


PROJECT:
Lora Bentleigh

17-19 Loranne Street,
Bentleigh


DEVELOPER:
Taylors Reynolds


Project update


June 2020
On the midst of these surreal times, it is business as usual at Lora Bentleigh. The Ground and First Floors are well underway with plastering. Levels two and three service rough in has been completed with windows on all levels installed.

It has been exciting watching the roof install and the external brickwork and cladding are ongoing.

As we will be sending out regular, important information from now until settlement, we need to ensure we have your correct contact information. Should your contact details change, please notify us at vhogg@360propertygroup.com.au

If you have any further enquiries or your contact information changes, please contact Vicki Hogg on vhogg@360propertygroup.com.au.



PROJECT:
River One

6 Joseph Road,
Footscray


DEVELOPER:
Blue Earth


ARCHITECT:
CHT Architects


Project update

  • Expected Construction Completion: Early 2021
  • Expected Settlement: April 2021
  • Contact: meg@blueearth.com.au

September 2020
River One is progressing to programme thanks to the great work of Hamilton Marino Builders.
 
Onsite, the structural works are well underway. The tower crane has been operational for several months and is scheduled to be removed by end of Feb 2021.
 
Externally, the structural core has been completed up to level 25, with surrounding slabs at level 21 this week. We expect the entire external structure/slabs to be capped out by the end of 2020. Capping out the structure will allow us to make the building watertight. 
 
Following the structure is the window systems, all feature architecture elements, wall finishing, and balustrading. 
 
Internally, the various trades including carpenters, joinery makers, electricians, fire sprinklers, plumbers and plasterers are sequentially working their way up the building as best they can with reduced numbers due to covid-19 restrictions.
 
We hope to have a larger workforce here commencing late September subject to government regulations.
 
In relation to the programme, the status is as follows:
 
Programme
The key programme items are as follows:
            
Stage                                     Status
  1. Site set up works                 Completed
  2. Bulk excavation                    Completed
  3. Basement works                  Completed
  4. Structure works                    In progress
  5. Services rough in                 In progress
  6. Window glazing                  In progress
  7. Facade cladding                   In progress
  8. Internal fit out works           In progress
  9. Finishing works
  10. Title registration
  11. Occupancy permit
  12. Ready to settle
 
Moving forward, we will continue to provide you with regular updates.
 
Filming of Waterfront Click on Link below:
 
Settlement Date
Settlement is anticipated for April 2021. 
 
COVID -19 Update 

The Victorian Government introduced on 2 August 2020 Stage 4 restrictions, which have reduced the workforce permitted on-site down to 25% of the prior levels and limited the production of off-site materials. 
 
Construction work is continuing, with Hamilton Marino rescheduling the various trades to get the most efficient progress possible in the circumstances. The Stage 4 restrictions currently apply with construction commencing back to 85% of production from 28th September 2020. 
 
At this stage we cannot determine the impact (if any) on the delivery program until the restrictions have eased and the construction industry is back to normal. 
 
We will keep you updated as we get closer to this date.
 
Contact Person
Meg is your dedicated contact person for all matters relating to construction updates and settlement. Meg’s details are as follows:
 
Name:            Meg Loughridge 
Email:             meg@blueearth.com.au
Phone:           0427 444 444




PROJECT:
Elysian

711 Barkly Street,
West Footscray


DEVELOPER:
Branson Property Group


Project update

25 September 2020

SETTLEMENT UPDATE - VALUATION INSPECTION

Construction of the project is in the final stages and valuation inspections can now be arranged with Branson's office, between 26/10/2020 and 30/10/2020, 9am-4pm.

To arrange your valuation inspection, please contact Mariah Spiteri on 03 9370 9111 or mariah@bransongroup.com.au.


25 September 2020

FINAL SETTLEMENT UPDATE

Construction of the project is in the final stages and pre-settlement inspections can now be arranged with Branson's office, between 9/11/2020 and 13/11/2020, 9am-4pm.

To arrange your valuation inspection, please contact Mariah Spiteri on 03 9370 9111 or mariah@bransongroup.com.au.

PROJECT:
Casey Green

96-166 Centre Rd,
Narre Warren


DEVELOPER:
Osanrae


ARCHITECT:
Demaine


BUILDER:
Demaine


Project update

  • Expected Construction Completion: End 2020/Early 2021
  • Expected Settlement: End 2020/Early 2021
  • Contact: admin@osanrae.com.au

Stage 6 Project Update - September 2020

The following works have taken place on site since the last update:
  • Timber framing works 90% complete
  • Structural steel works 100% complete
  • External cladding works 80% complete
  • Windows and roof tile works 90% complete
  • Plastering works 80% complete
  • Internal fitout and finishing works commenced
  • Driveways and external fencing works 80% complete
  • Landscape works commenced

Works planned on site for the next quarter of 2020:
  • Completing all remaining internal and external works
  • Performing final cleans and defect inspections
  • Preparing for settlement and handover

Anticipated settlement:
Lots 106 to 116 – End 2020
Lots 117 to 127 – End 2020
Lots 241 to 245 – End 2020
Lots 139 to 150 – Early 2021

We will continue to update quarterly. In the meantime, if you have any queries regarding the development please contact nhan@360propertygroup.com.au.



Make an enquiry